CalendarStart date: Aug 2016 – Completion date: Jun 2017

LocationLocation: Fishponds, Bristol

ArrowMain Contractor: Juniper Homes

PoundValue: £150k

Scope of works:

This former chapel was renovated to the highest standards to provide 7 luxury apartments along with a new build of 7 more.  Set over 4 floors SWI had to upgrade sound, fire & insulation to existing walls & ceilings, form new twin stud party walls & partitions and skim throughout.

SWI carried out the following works;

  • Metal stud partitions; twin ‘I’ stud & C stud
  • Plasterboarding
  • Dot & dab
  • MF ceilings
  • Plastering
  • Rendering